Design : SWMD: Copley Ditch (County Ditch #38)
LAST UPDATED:
Jun 2, 2026
Project Details
Communities:
Copley Township
Project Schedule
Plan Year:
01-01-2026 - 12-31-2026
This project is the result of two studies described on the webpages of Copley Ditch and Black Pond Outlet Study and the Copley Meadows Study.
Status:
This project design is 90% complete and construction is planned for 2027.
- 04/2/2026: Tree Cutting has been completed in this area.
- 05/14/2026: County Council is having a public hearing on June 15th.
- ATT A: Copley Ditch Petition Signed (PDF, 6247.4k)
- ATT B Copley OPCC Final (PDF, 233.8k)
- ATT C Copley Ditch Drainage Improvement - ODNR Comments (PDF, 624.8k)
- ATT D Copley Ditch Schedule of Values & Assessments (PDF, 428.9k)
- ATT E Copley Ditch Easement Dedication Plat (PDF, 3799.8k)
- ATT F Copley Ditch Bid Set 2026 (PDF, 36655.3k)
- ATT F2 Copley Ditch Revised Plans 10&16 2026 (PDF, 1415.9k)
- Engineer’s Final Report to Council - Copley Ditch (PDF, 142.5k)
- Copley Ditch Public View (PDF, 3980.6k)
- Copley Ditch Legal Notice Including Petition (PDF, 3479.2k)
- Copley Twp Legal Notice & Supporting Documents to Landowners (PDF, 3479.2k)
- Copley Ditch Prelim Engineering Report (PDF, 6526.3k)