Design : SWMD: Hinman Ditch: Stormwater Basin and Channel Improvements, Ditch #52 (Penguin Area Improvements)
LAST UPDATED:
Mar 24, 2026
Communities:
Coventry Township
Design Consultant:
Environmental Design Group
Plan Year:
01-01-2023 - 12-01-2024
Construction Starts:
Jan 1, 2027
Construction Finish:
Dec 31, 2027
This project will construct 5 acres of SWM basins and/or bankfull wetlands, replace a culvert under Glenmount Ave, and improve stream channel at 2 locations: A) west of Glenmount Ave/ north of US224 and B) north and east of Penguin Apartments.
Status:
This project is in the final design stage. The final design report will be submitted by November 30, 2026. A final public hearing and request for authorization to move to the construction phase will occur in 2027.
Location:
In Coventry Township benefitting Brewster Creek and the Tuscarawas River Watershed.
- Hinman Ditch Special Meeting 05/13/2025 Presentation (PDF, 8178.4k)
- Coventry Twp (Hinman Ditch Petition) Legal Notice & Supporting Documents (PDF, 2571.4k)
- Stormwater Basin and Channel Improvements, Hinman Ditch, Ditch #52 Study (PDF, 16739.1k)
- Hinman Ditch Public Viewing 20JUL2025 (PDF, 8977.0k)
- Prelim. Report. Coventry Township 10/02/2025 (PDF, 15070.0k)