Construction : Valley View Road Resurfacing Part II

LAST UPDATED:

Nov 13, 2025

Project Details

Project ID:

116703

Communities:

Northfield Center

Project Contacts:

Project Engineer:
Sam Ross, P.E.

Project Manager:
Chuck Hauber, P.E., P.S. 

Design Consultant:

EDG 

Project Schedule

Plan Year:

08-21-2025 - 05-31-2026

Roadway Minor Rehabilitation, The existing roadway will be milled, widened, and overlaid from approximately 400 feet west of the Olde 8 Road intersection to the intersection with Dunham Road. Substandard shoulders will be widened and improved where feasible, while maintaining the existing cross slopes. Additionally, the northwest-bound approach at the North Boyden Road intersection will be widened to accommodate a revised lane configuration, including a dedicated left-turn lane.

Status:

Kenmore Construction has been awarded this project. 

  • 10/29/2025: Contract between SCE and contractor has been signed. Preconstruction meeting has be scheduled for the end of next week
  • 11/13/2025: Preconstruction meeting was held last Thursday. Kenmore is planning on starting the project in the last week of March 2026

Maintenance of Traffic:

This resurfacing project will require closure of Valley View Road. Routes will be posted prior to construction

Image of Valley View Resurfacing Part II

Costs

Total:

$921,156.72

Funding Sources:

Local Share: $133,656.75

ODOT Funding: $787,500.00