Construction : Valley View Road Resurfacing Part I

LAST UPDATED:

May 16, 2024

Project Details

Project ID:

108141

Communities:

Northfield Center

Project Contacts:

Chuck Hauber, PE

Design Consultant:

Part of a task order contract with Environmental Design Group

Project Schedule

Plan Year:

05-01-2024 - 10-30-2024

This project will repair, resurface, and add 4 foot wide shoulders where possible to 0.4 miles of Valley View Road between Olde 8 Road and State Route 8 in Northfield Center Township. 

Status:

Barbicas Construction is in the low bidder on this project. 

  • 10/04/2023: The contractor has begun work
  • 11/14/2023: Barbicus is finishing yard drains and weather permiting will be installing surface course tomorrow
  • 11/21/2023: Road has been paved and will need final stripping in Spring due to weather.
  • 01/02/2024: Work is Substantially complete.  Will need to touch up landscaping and do striping in the spring.
  • 05/07/2024: Contactor has completed seeding and muilding. Subcontractor that is to complete pavement markings is on site. 
  • 05/16/2024: Subcontractor has completed pavement markings.

County/Route/Section:

County Highway 16

Graphical map of project site

Maintenance of Traffic:

This resurfacing project will require closure of Valley View Road. Traffic will be detoured utilizing State Route 8 and Olde 8 Road.

Image of Valley View Resurfacing Part 1 project image

Costs

Project Development Cost:

$130,000.00

Construction Cost:

$335,000.00

Total:

$465,000.00

Funding Sources:

Federal Surface Transportation Block Grant Funding: $265,000.00

Motor Vehicle and Gas Tax Funds: $205,000.00