Construction : Swartz Road Resurfacing Project

LAST UPDATED:

Oct 5, 2023

Project Details

Project ID:

113176

Communities:

Coventry Township

Project Contacts:

Chuck Hauber

Project Schedule

Plan Year:

06-01-2023 - 12-15-2023

Resurfacing and shoulder widening of Swartz Road beginning at S. Main and ending at the Akron Corp limits, near Penguin Drive. Construction is tentatively scheduled to begin in August 2023 and last approximately 60 days. Construction was originally planned for 2025 but the funding was made available sooner so the project was moved up. The County has received $500,000 in funding from STBG Funding Program (AMATS) Estimated cost $952,500.

Status:

Karvo is the low bidder for this project. The start date of this project was August 24, 2023. The contractor has completed the widening of the roadway along with the installation of the intermediate and surface course. Currently the contractor is working on grading and driveways. 

Graphical map of project site

Maintenance of Traffic:

Traffic will maintained during construction.

Image of Swartz between Penguin and S Main

Costs

Construction Cost:

$952,500.00

Funding Sources:

Federal STBG funds: $500,000

 Local funds: $452,500