Design : SWMD - Wye Road Drainage Improvements Phase 2
LAST UPDATED:
May 1, 2024
Communities:
Bath Township
Project Contacts:
Dave Koontz, PE
Design Consultant:
ms consultants, inc
Plan Year:
06-01-2023 - 06-01-2025
This project will be done in two phases. Phase 2 will modify existing stormwater management basins and add best management practices such as step-pools, cascades, and riffles at four locations along the stream in the ravine at the northern edge of the Sanctuary of Bath Estates It will also include cleaning out an existing storm sewer along Wye Road and perform minor clean up and erosion repairs along the stream.
Status:
Design for Phase 2 is about 95% complete with construction scheduled for Fall of 2024 through Spring of 2025.
Location:
In Bath Township benefitting the Yellow Creek Watershed.