Completed : SWMD: Stubbins and Farnham Drainage Improvements

LAST UPDATED:

Mar 23, 2026

Project Details

Communities:

Richfield Township

Project Schedule

Plan Year:

01-01-2025 - 12-31-2025

This project will construct wetlands and improve ditches in the Stubbins/Farnham area.

Status:

Richfield and SCE successfully obtained OPWC funds for this project. Construction is substantially complete. 

Location:

In Richfield Township benefitting a tributary to the Cuyahoga River Watershed.

Image of Stubbins/Farnham Map

Costs

Construction Cost:

TBD

Funding Sources:

American Rescue Plan Act funds

Possible OPWC grant funds