Design : Glenwood Dr. Bridge Replacement

LAST UPDATED:

Mar 19, 2026

Project Details

Communities:

Twinsburg

Design Consultant:

Michael Baker International

Project Schedule

Plan Year:

10-01-2027 - 11-01-2028

This project will be a complete replacement of the existing structure. It is located just West of Gary Drive in the city of Twinsburg. SCE is partnering with the City of Twinsburg to widen the bridge and provide additional pedestrian-friendly features. 

Status:

Design work is underway and extra precautions are being taken to preserve the bat population near the bridge. Construction is anticipated in 2027. 

Graphical map of project site

Maintenance of Traffic:

To be determined in the design phase. 

Image of Glenwood Dr over Tinkers Creek POV

Costs

Total:

$3,476,000

Funding Sources:

Local Major Bridge Program: $2,602,160

Local Funding: $600,000