Construction : Canton Road and Sanitarium Road Intersection Improvement

LAST UPDATED:

Mar 18, 2026

Project Details

Communities:

Springfield Township

Project Contacts:

Brian Olson, PE

Project Schedule

Plan Year:

01-01-2026 - 05-31-2025

This project will upgrade the existing traffic signal and add a sidewalk from the Springfield High School north driveway entrance to Sanitarium Road. Project work will also include additional curbing with ADA ramps, crosswalks, and pedestrian push buttons to activate the pedestrian signals.

Status:

Perram Electric is the low bidder on this project. Construction work is underway. This has an anticipated completion date of May 31, 2026. 

Maintenance of Traffic:

Traffic will be maintained throughout the project.

Image of Canton Road and Sanitarium Road Map

Costs

Total:

$356,680.00

Funding Sources:

Motor Vehicle and Gas Tax Funds