Proposed : Akron-Peninsula Rd. Bridge Replacement

LAST UPDATED:

Mar 18, 2026

Project Details

Communities:

Boston Township

Project Schedule

Plan Year:

01-01-2030 - 12-31-2030

This project will be a complete replacement of the existing 28 ft long by 34 ft wide Akron Peninsula Rd. Bridge over Salt Run. It is located just south of Truxell Road in Boston Townhip. 

Status:

We are applying for 2026 CEAO LBR funds for this bridge replacement. If we are successful in getting grant funds, design will begin in 2027 with an anticipated construction year of 2030. 

Graphical map of project site

Maintenance of Traffic:

To be determined in the design phase.

Image of Akron Peninsula Bridge Over Salt Run POV 02/22/2024

Costs

Total:

$1,480,000

Funding Sources:

To be determined.