Construction : Riverview Road Bridge over Furnace Run Replacement Project

LAST UPDATED:

Mar 18, 2020

Project Details

Project ID:

105067

Communities:

Cuyahoga Falls

Project Contacts:

Sam Ross PE, Construction Section Manager

Design Consultant:

E.L. Robinson

Project Schedule

Plan Year:

04-01-2020 - 08-31-2020

Bid Due Date:

Oct 18, 2019

Bid Awarded:

Nov 15, 2019

Construction Starts:

Feb 10, 2020

Construction Finish:

Jun 15, 2020

Located in the City of Cuyahoga Falls, north of the Riverview Road intersection with Bolanz Road, the existing bridge is to be reconstructed in 2020. The work will include replacing the bridge deck and  portions of the piers and abutments supporting the bridge deck.  A new precast concrete box beam structure will be constructed on top of the reconstructed support members and a new concrete deck will be poured on top of the box beams. Construction started in February and the bridge reopen contract date is June 15, 2020. 

Status:

The construction contract was awarded to J.D. Williamson Construction Co., Inc. 

Graphical map of project site

Maintenance of Traffic:

The bridge will be closed for the duration of the project. The detour route is Bolanz to Akron-Peninsula to State Route 303 back to Riverview Road. Access to Salazy’s Farm market will be maintained at all times from the Bolanz Road driveways, but the Salazy’s driveway to Riverview Road will be closed during construction.  The existing hike and bridle trail crossing of Riverview Road will be temporarily re-located north approximately 100 feet to permit the proper installation of temporary concrete barriers to protect the motorists and the workers. 

Image of Riverview Road over Furnace Run Photo

Costs

Project Development Cost:

$213,316.00

Construction Cost:

$1,239,851.13

Total:

$1,453,167.13

Funding Sources:

CEAO Local Bridge Program funds: $1,268,800.00

Toll Road funds: $317,200.00