Construction : NOW OPEN: Pressler Road Bridge over the South Fork of the Tuscarawas River Replacement Project
LAST UPDATED:
Dec 4, 2023
Project ID:
113152
Communities:
Springfield Township
Project Contacts:
Chuck Hauber, PE, PS
Design Consultant:
ms consultants, inc.
Plan Year:
04-01-2023 - 11-30-2023
Construction Starts:
Apr 1, 2023
Construction Finish:
Nov 30, 2023
This project will replace the poor condition, structurally deficient, load posted two-span concrete slab structure a new structure. Design is scheduled for 2021 and 2022 and construction is anticipated for 2023.
Status:
**The bridge reopened to traffic on 12/8/23**
Black Horse Bridge is the contractor for this project. Construction on this project started on 8/24/2023. Since the demolition of the original structure, piles have been driven, footers were formed, beems were set, deck was poured, road was paved, and gooving was completed. Weather permiting, this project will be completed this spring once permanent stripping is completed.
Location:
On Pressler Road approximately 0.2 miles south of Killian Road, in Springfield Township.