Design : Pressler Road Bridge over the South Fork of the Tuscarawas River Replacement Project
LAST UPDATED:
Dec 23, 2020
Project Details
Project ID:
113152
Communities:
Springfield Township
Project Contacts:
Chuck Hauber, PE, PS
Project Schedule
Plan Year:
01-15-2021 - 09-29-2023
Construction Starts:
Apr 1, 2023
Construction Finish:
Nov 1, 2023
This project will replace the poor condition, structurally deficient, load posted two-span concrete slab structure a new structure. Design is scheduled for 2021 and 2022 and construction is anticipated for 2023.
Status:
SCE is starting the process to hire a consultant to perform bridge design services.
Location:
On Pressler Road approximately 0.2 miles south of Killian Road, in Springfield Township.