Construction : Pressler Road Bridge over the South Fork of the Tuscarawas River Replacement Project
LAST UPDATED:
Jan 17, 2023
Project Details
Project ID:
113152
Communities:
Springfield Township
Project Contacts:
Chuck Hauber, PE, PS
Design Consultant:
ms consultants, inc.
Project Schedule
Plan Year:
04-01-2023 - 11-30-2023
Construction Starts:
Apr 1, 2023
Construction Finish:
Nov 30, 2023
This project will replace the poor condition, structurally deficient, load posted two-span concrete slab structure a new structure. Design is scheduled for 2021 and 2022 and construction is anticipated for 2023.
Status:
Black Horse Bridge is the apparent low bidder for this project and the construction contract is going through the County approval process.
Location:
On Pressler Road approximately 0.2 miles south of Killian Road, in Springfield Township.