Completed : Medina Line Road Resurfacing Phase 2

LAST UPDATED:

Oct 25, 2019

Project Details

Project ID:

103065

Communities:

Bath Township

Project Contacts:

Sam Ross, PE, Construction Section Manager

Project Schedule

Plan Year:

07-01-2019 - 10-31-2019

This project is substantially complete, with additional clean-up work to be done in the spring of 2020. This project resurfaced Medina Line Road from State Route 18 to Granger Road, including full and partial depth repairs, shoulder reconstruction, drainage repairs, pavement markings, curbing, guardrail, loop detector replacement, and driveway approaches. This project also included paving four foot wide shoulders, making the roadway safer for cyclists and pedestrians. 

Status:

Work is substantially complete.

County/Route/Section:

County Highway 2

Location:

On Medina Line Road between State Route 18 and Granger Road.

Maintenance of Traffic:

Traffic will be maintained at all times.

Image of Medina Line Road Resurfacing Map

Costs

Construction Cost:

$1,411,160.86

Funding Sources:

Federal Surface Transportation Block Grant funding: $743,600.00

Motor Vehicle and Gas Tax funding: $667,560.86