Construction : NOW OPEN - Brandywine Road Bridge over Brandywine Creek
LAST UPDATED:
Sep 9, 2022
Project Details
Communities:
Northfield Center
Project Contacts:
Neal Measle, PE
Design Consultant:
Osborn Engineering
Project Schedule
Plan Year:
02-26-2022 - 12-31-2022
This bridge is now open. This project included rehabilitation of the existing three-span, continuous steel beam structure (Structure No. NOR-040-0157) carrying Brandywine Rd (CR 40) over the Brandywine Creek. Rehabilitation items included: new reinforced concrete deck, new bridge railing, new beam bearings, structural steel repairs, field painting of structural steel, substructure repairs, new reinforced concrete approach slabs, and minimal approach roadway work (pavement, drainage, guardrail, etc.).
Status:
The bridge rehabilitation work is substantially complete and the road is now open.
County/Route/Section:
County Route 40, Section 1.57