Location:
Description of Work: This project involves reconstruction of the existing Cleveland-Massillon Road Bridge No. BAR-017-0708 over Hudson Run with similar alignment and profile and minimal approach work. The replacement bridge will be widened by increasing northbound & southbound lane widths to current design standards, adding a new center turning lane, shoulder widening and providing additional 5 feet east side sidewalk all to match the proposed Cleveland-Massillon (31st Street) Roadway improvements administered by the City of Barberton.
Maintenance of Traffic: Traffic will be detoured during reconstruction of the Cleveland-Massillon (31st Street) Road Bridge utilizing local roads approved by the City of Barberton.
Estimated Schedule: April 9, 2012 - August 10, 2012
Contact: Geordie Kissos