General Description

Print

Location

JavaScript must be enabled in order for you to use Google Maps.
However, it seems JavaScript is either disabled or not supported by your browser.
To view Google Maps, enable JavaScript by changing your browser options, and then try again.



RAVENNA ROAD BRIDGE OVER TINKERS CREEK AND OLD MILL ROAD/STOW ROAD INTERSECTIONS
 

Updated: July 9, 2010

County/Route/Section No: SUM-CR 12/109-1.40/1.72

Project Identification No. (PID): 82787

Communities: Twinsburg Township

Project Location: Along Ravenna Road approximately 350 feet south and north of the Ravenna Road/Old Mill Road intersection. Along Old Mill Road approximately 350 feet west and south of the Old Mill Road/Stow Road intersection to approximately 350 feet east of the Ravenna Road/Old Mill Road intersection.

Description of Work: This project involves reconstruction of the existing Ravenna Road Bridge No. TWT-012-0140 over Tinkers Creek with similar alignment and profile. The project also includes application of new pavement markings, new approach guardrail and traffic control devices. The project provides for reconstruction of the Ravenna Road/Old Mill Road and Old Mill Road/Stow Road intersections.  Temporary pavement will be required for maintenance of traffic.

Maintenance of Traffic: Traffic will be detoured during the reconstruction of the Ravenna Road Bridge. The preferred detour route will be reviewed at the Public Involvement Meeting. Bi-directional traffic will be maintained during reconstruction of the Ravenna Road/Old Mill Road and Old Mill Road/Stow Road intersections utilizing temporary pavement.

Summary of Costs:
      Project Development Cost: $780,000 Estimated
      Construction Cost: $4,173,000 Estimated
      Total Project Cost: $4,953,000 Estimated
    
Funding Sources:
      FHWA (CEAO/HSIP): $1,300,000
      FHWA (CEAO/LBR): $1,420,000
      Summit County Engineer (SCE): $2,233,000

Schedule:
      Bid Date: February 21, 2012 Estimated
      Award Date: February 29, 2012 Estimated
      Construction Start: March 19, 2012 Estimated
      Construction Finish: November 30, 2012 Estimated
    
Status: LPA Project Scope for programming submitted on April 18, 2007. ODOT ELLIS Reporting issuing PID 82787 on May 9, 2007. LPA Field Review Meeting conducted on May 10, 2007. Final Development Phase Scope of Services approved on July 13, 2007 with final revision dated March 10, 2008. Consultant advanced authorization to proceed for Field Survey and Preliminary Design Alternatives issued on March 5, 2008. Professional Design Services Agreement fully executed on April 28, 2008. Project Red Flag Summary received on June 12, 2008 with SCE comments transmitted on July 10, 2008. ODOT Office of Technical Services provides Certified Traffic on July 28, 2008 in response to WEQ July 22, 2008 request. Preliminary Engineering - Alternatives Analysis Study received on August 29, 2008. Compliance Preliminary Engineering - Alternative Analysis Study received on December 31, 2008. March 6, 2009 senior staff email requests additional Study Alternative to eliminate southbound right turn lane on Ravenna Rd, provide additional Ravenna Rd profile and an aesthetically pleasing arch type bridge replacement option. SCE July 1, 2009 approves WEQ Revised (1) Preliminary Engineering - Alternative Analysis Study contract fee modification by utilizing existing contract If Authorized items likely to be non-performed. WEQ August 6, 2009 submits Revised (1) Preliminary Engineering - Alternative Analysis Study. September 8, 2009 WEQ responds to ODOT D4 August 31, 2009 preliminary comments. August 15, 2009 ODOT D4 requests copies of October 25, 2007 Intersection Safety Studies for each intersection. ODOT D4 November 9, 2009 provides additional comments to Revised Preliminary Engineering - Alternative Analysis Study. SCE February 11, 2010 meeting with WEQ requests Revised (2) Preliminary Engineering - Alternative Analysis Study.  SCE April 26, 2010 Change Order No. 1 approves WEQ March 25, 2010 Modification No. 2 for Revised (2) Preliminary Engineering - Alternative Analysis Study.  WEQ submits Revised (2) June 2010 Preliminary Engineering - Alternative Analysis Study.  SCE review ongoing with project status meeting scheduled with ODOT D4 of July, 15, 2010.  Public Meeting to present Preliminary Engineering - Alternative Analysis Study to be scheduled in early September, 2010.    

Design Consultant: W. E. Quicksall and Associates, Inc.


Project Contact:  Geordie Kissos, P.E., Public Works Manager

Last Updated on Tuesday, 13 July 2010 11:59