Location:
Posted: January 5, 2009
Bridge ID: SUM CR27-04.35
County/Route/Section No: SUM CR 27-04.35
Project Identification No. (PID): Pending
Communities: The City of Cuyahoga Falls
Project Limits: Northampton Road over Mud Brook, located approximately 0.8 miles north of Portage Trail Road Extension
Description of Work: The purpose of this project is to replace the existing bridge over Mud Brook by removing the existing bridge (County Bridge No. CUY-027-0435, SFN 7745095) and constructing a new bridge, approach slabs, and stream bank protection/stabilization.
Maintenance of Traffic: Traffic will be detoured during construction. The detour route will be posted.
Summary of Costs:
Estimated Project Development Cost: $160,000
Estimated Right-of-Way Costs: $25,000
Estimated Construction Cost: $560,000
Estimated Construction Engineering Costs: $56,000
Total Estimated Project Cost: $801,000
Funding Sources:
CEAO (LBR Funds): $400,000
Summit County Engineer (SCE): $401,000
TOTAL: $801,000
Estimated Schedule:
Bid Date: July 1, 2009
Award Date: July 8, 2009
Construction Start: September 1, 2009
Construction Finish: November 30, 2009
Status: The request for Technical Proposals from selected consultants was issued on October 1, 2007. Technical Proposals were received on October 26, 2007. Based on evaluation of the Technical Proposals, Michael Baker Jr., Inc., was selected to provide professional engineering services. The request for a fee proposal was submitted to Michael Baker Jr. on December 18, 2007. The fee proposal was received on January 7, 2008. A revised fee proposal was received on March 18, 2008. Fee negotiations were finalized in May 2008. On June 11, 2008, the County's Board of Control awarded the design contract to Michael Baker, Jr., Inc. A Kick-off meeting was held on June 13, 2008, and the design of the project officially began. The Consultant was authorized to proceed on June 1, 2008. Stage 1 plans were received on August 8, 2008 and comments were returned to the consultant on September 4, 2008. Stage 2 plans were received on November 10, 2008, and are under review.
Design Consultant: Michael Baker Jr., Inc.
Project Contact: Robert Sobnosky, P.E., Construction Section Manager