General Description

Print

Location:

JavaScript must be enabled in order for you to use Google Maps.
However, it seems JavaScript is either disabled or not supported by your browser.
To view Google Maps, enable JavaScript by changing your browser options, and then try again.

HAZEL STREET BRIDGE OVER LITTLE CUYAHOGA RIVER

Updated: July 9, 2010

County/Route/Section No.: SUM-CR 653-0.25

Project Identification No. (PID): 22079

Communities: City of Akron

Project Location: The bridge is located on Hazel Street over the Little Cuyahoga River approximately 800 feet west of Wellington Avenue in the City of Akron.

Description of Work: This project involves the replacement of the bridge superstructure, the repair of the bridge substructure, reconstruction of the approach roadway, application of new pavement markings and new guardrail and traffic control devices.

Maintenance of Traffic: Bi-directional traffic will be maintained during all three construction phases utilizing temporary pavement when necessary.

Summary of Costs:
Project Development Cost: $161,722 Actual
Construction Cost: $664,595 Actual
Total Project Cost: $826,317 Actual
 
Funding Sources:
FHWA (CEAO/LBR): $557,600
OPWC State Issue 1: $536,800
Summit County Engineer (SCE): $71,600
City of Akron (COA): $50,000

Schedule:
Bid Date: March 23, 2010 Actual
Award Date: April 7, 2010 Actual
Construction Start: May 12, 2010 Actual
Construction Finish: November 30, 2010 Estimated
 
Status: Plans, Specifications and Engineers Estimate submitted to ODOT D4 on December 7, 2009.  Lockhart Concrete began construction on May 12, 2010.  Phase 1 construction completed June 25, 2010 with Phase 2 construction ongoing.

Design Consultant: GPD Group/ACLA

 

Project Contact: Geordie Kissos, P.E., Public Works Manager


 

Last Updated on Tuesday, 13 July 2010 10:02