Location:
Updated: March 27, 2009
County/Route/Section No.: SUM CR 17-14.14
Project Identification No. (PID): 81697
Status: The request for Technical Proposals was issued to 5 short-listed consulting firms on June 4, 2008. The Technical Proposals were received on June 27, 2008. The Technical Proposals have been evaluated and URS Corporation was selected as the top-ranked consultant. A scope meeting was held on August 26, 2008. A request for a fee proposal was submitted to the consultant on August 27, 2008. The fee proposal was received on September 17, 2008. The fee proposal was revised and accepted on October 15, 2008. The County's Board of Control awarded the contract to URS Corporation on October 22, 2008. County Council is expected to confirm the award on January 12, 2009.
Communities: Copley Township and City of Fairlawn
Project Limits: Cleveland-Massillon Road between the intersections with Ridgewood Road and the required approach roadway. Conceptual plans of the alternatives being considered can be seen here:
Description of Work: The purpose of this project is to improve the operation and safety of the Cleveland-Massillon Road/Ridgewood Road intersections by realigning Ridgewood Road or by constructing one or two modern roundabouts to replace the existing signal-controlled intersections. The project involves the improvement of the intersection(s) by removing the existing pavement; grading; realigning Ridgewood Rd. or constructing one (or two) modern roundabout(s) consisting of asphalt concrete pavement, truck apron(s), splitter islands, and center island(s); constructing sidewalk; reconstructing storm sewers; removing existing traffic signal equipment; applying pavement markings; installing traffic signs; coordinating utility relocations; and acquiring permanent and temporary right-of-way.
The project will proceed in three phases. The first phase (Preliminary Engineering Phase) will involve an engineering study to determine the preferred alternative. The second phase (Final Development Phase) will involve the preparation of the construction plans, environmental studies, and right-of-way acquisition. The third phase will be construction of the planned improvements.
Maintenance of Traffic: Traffic will be maintained during construction using part-width construction.
Summary of Costs:
Estimated Project Development Cost: $220,000
Estimated Right-of-Way Costs: $45,000
Estimated Construction Cost: $975,000
Estimated Construction Engineering Costs: $110,000
Total Estimated Project Cost: $1,350,000
Funding Sources:
CEAO/Federal (STP Funds): $912,000
Local Funds (City of Fairlawn and Summit County Engineer): $438,000
Total: $1,350,000
Estimated Schedule:
Begin Preliminary Engineering (Alternative Analysis): January 15, 2009
Complete Preliminary Engineering: March 15, 2009
Begin Final Design: May 1, 2009
Bid Date: March 1, 2012
Award Date: March 15, 2012
Construction Start: April 15, 2012
Construction Finish: August 30, 2012
Design Consultant: URS Corporation


